October 22, 2026
Every walk onto the Oceanside Pier starts on the white concrete bridge at the foot of Pier View Way. It runs out from the bluff at Pacific Street and passes over The Strand. The wooden deck stretches past the Bait Shop and the fish-cleaning station, and then a fence stops you short of the far end, where the April 2024 fire burned. That fence draws the eye, and it is the part with insurance coverage, a design team and a construction calendar.
The bridge you crossed to get there is the harder problem. It was built in 1927, it will be 100 years old next year, and as of early October its replacement was about $60 million short of funding. The two structures share one walkway but are on separate repair schedules, and the bridge's schedule is the less certain one.
The ATF found the hammerhead fire to be accidental. It most likely started with an electrical failure under the planks in the northwest corner of the pier head. The fire destroyed the vacant two-story building that once housed Ruby's Diner and the smaller Brine Box take-out kiosk. The City reopened about 90 percent of the pier on May 10, 2024, and the far west end has stayed closed ever since.
Since then, the hammerhead has moved through a clear sequence:
Building in that summer pause keeps the busiest months of the year free of deck work. The schedule depends on supplies as well as construction. In mid-September, City Engineer Brian Thomas reported that the repair design was about half complete and that permit applications and lumber orders were underway, a process that can take three to six months. "The lumber is going to take a long time to come from the Pacific Northwest," he told the Council on September 16, according to the San Diego Union-Tribune.
The money is set up the same step-by-step way. The City's latest estimate for the fire repairs is $17 million, which does not include rebuilding the restaurant or the kiosk. The City's losses are covered by its PRISM insurance program, and the restaurant tenant carries its own policy. As of March, the City had received only an initial payment toward demolition. According to Thomas, the rest will be based on the actual cost of restoring the hammerhead once the reconstruction contract is awarded.
The restaurant comes last. OS Pier LLC took over the lease after Ruby's Diner went bankrupt, and it has said it intends to rebuild. The City expects the new building to sit on roughly the old Ruby's footprint, but no design or timeline has been released. The City plans to reopen the hammerhead to the public before the restaurant is built. "Our goal, at the end of the day, is to open the end of the pier to the public, while the future restaurant is being designed and permitted," Thomas told the Union-Tribune.
The wooden pier is the newer part. The current deck, nearly 2,000 feet long, was built in the mid-1980s after winter storms wrecked the one before it. The concrete bridge connecting it to Pacific Street is from 1927, and seawater has been working into it for 99 years. Corroded steel rebar has caused whole chunks of concrete to break off. In 2021, a piece of interior ceiling fell onto a lifeguard administrator's desk in the lifeguard headquarters, which occupies the building under the bridge deck that was once a public dining hall. A 2018 consultant's study found that the span did not meet current seismic and structural standards. City Engineer Thomas told inewsource the concrete has an estimated life through 2030 and needs to be replaced, not repaired.
"She's turning 100 next year. She was only meant to go to 100, and she is crumbling, and she's becoming a public safety issue."
Oceanside Mayor Esther Sanchez, as reported by inewsource
After a series of community meetings, the consensus was to tear down the bridge and build a longer-lasting replacement that looks much like the original. The cost estimates have climbed with each update. inewsource reported a $60 million replacement estimate in August. The City's pier page lists an $80 million project with $11 million set aside. The most recent figure came from a September presentation to the Council and was reported on October 4. It put the total at about $82 million, with $9.7 million already spent on planning and another $12 million set aside.
The usual grant programs don't cover this kind of structure. Because the bridge carries no vehicle traffic, it doesn't qualify for Caltrans or Federal Highway Administration funding. The City is looking at sources such as Proposition 4, the 2024 state measure for parks, outdoor recreation and climate adaptation. Thomas told inewsource that the design could be finished by fall 2027 and construction could start by summer 2028.
The two projects side by side:
| Hammerhead | Pier View Way bridge | |
|---|---|---|
| Age of structure | Wooden pier, mid-1980s | Concrete, 1927 |
| Latest cost estimate | $17 million | About $82 million |
| Funding source | PRISM insurance program | $9.7M spent, $12M set aside, about $60M short |
| Next step | Bracing contract, then deck work spring 2027 | Finish design and environmental review, then permits |
| Earliest construction | Spring 2027 | Summer 2028, per the City Engineer |
The bridge is part of the reason Oceanside has a sales tax on Tuesday's ballot. Measure S would add a half-cent general sales tax for 10 years. The City estimates it would raise about $20 million a year, with independent citizen oversight. Because it is a general tax, the money could go to any lawful city purpose. The ballot text lists streets, sidewalks, parks, public facilities, beach protection and public-safety facilities.
inewsource reported that the pier bridge is one of five infrastructure projects city officials have said they might pursue with the new revenue. If the measure passes, Oceanside's rate would rise to 8.75 percent, tying it with Del Mar, Escondido, San Marcos, Solana Beach and four other cities for the highest rate in the county. The Council voted unanimously in August to put the measure on the ballot. Some residents have objected to the process and argue that a sales tax falls hardest on lower-income households. The bridge doesn't depend on Measure S alone, but the measure will help decide how fast the bridge's funding gap closes.
For now, the pier is open from 4 a.m. to 10 p.m. every day, from the bridge to the last offset past the restrooms and fish-cleaning station. Oceanside Pier & Bait Shop sits mid-pier and rents rods and sells bait, tackle and snacks.
From The Strand, you can see the bridge's interim care. Crews are patching the worst areas of concrete and hanging safety netting underneath, so scaffolding may appear below the deck. The Strand is busy for other reasons, too. The City's Downtown Water and Sewer Replacement Project Phase II began in March 2026 and is expected to run into 2028. During that work, North Strand is closed to through traffic, with access only for residents and emergency vehicles.
Oceanside's beaches head into winter with new sand. The U.S. Army Corps of Engineers moved its harbor dredge from spring to fall this year as a trial. About 395,000 cubic yards of sand was placed on Oceanside beaches, with placement starting September 15 and moving south toward Tyson Street Park, and the dredge finished October 7. The City says fall placement allows northwest winter swells to carry the sand south toward the most eroded stretches of coast ahead of what it expects to be a strong El Niño winter.
The City is also restoring the names engraved in the pier railing during Oceanside's 1988 centennial. About 95 percent of them survived the fire, and the City is working to replace the ones that were lost. The award and start date for the hammerhead bracing contract will be posted on the City's pier recovery page when they're settled. Every Thursday from 5 to 9 p.m., the Sunset Market runs along Pier View Way, the street the bridge is named for.
Big public projects like the bridge replacement and the hammerhead rebuild can affect how a coastal home is valued and presented. If you own near the pier and want to know how the 2027–2028 work schedule fits your plans, Cathleen Shera Team offers a complimentary home valuation and private consultation built around those dates.